Multilateral funders often restrict the origin of goods to a list of member countries. UNDP takes the opposite approach: as a rule, equipment may come from any country and bidders may be of any nationality. Restrictions do exist, but they are exceptions and must be written into the documents of each solicitation.

This guide explains where to find them, based on UNDP's invitation to bid (ITB) template and the POPP policies, and what they mean for a supplier putting together an offer for equipment made in several countries.

Updated on 21 October 2026

Open origin unless the Data Sheet says otherwise

The "Eligible goods, works and services" clause of the ITB template sets the principle: goods may originate in any country except those listed, if any, in the Data Sheet (Section 3). The Data Sheet is therefore the first thing to read. If it is silent on origin, no country of manufacture is excluded.

The template defines origin as the place where goods are mined, grown or produced. Goods are produced where manufacturing or substantial assembly of components results in a commercially recognised product that is substantially different from its components. Origin is therefore declared at the place of actual manufacture, not the place of shipment.

Bidder nationality and sanctions lists

The template keeps origin of goods separate from the nationality of the bidder. A company takes the nationality of the country where it is incorporated and lawfully operates, and again only nationalities named in the Data Sheet are barred.

The real barriers lie elsewhere. A bidder is ineligible if it appears on the UN Ineligibility List hosted by UNGM, on the Security Council Consolidated Sanctions List, including the 1267/1989 list, or on the World Bank debarment listings. For a consortium or group, every company must meet these conditions. A government-owned firm faces an additional review of its independence and subsidies.

When a donor wants restrictions

UNDP projects are often financed by a government or institution making a contribution, and that donor may wish to limit countries of origin. The Procurement Methods policy, however, forbids offices from placing restrictions on bidders' countries of origin in solicitation documents. Where a funding agreement contains such a limitation, the office needs prior approval from the Chief Procurement Officer before the agreement is finalised.

The Procurement Overview and Principles policy says the same: no contracts reserved to exclusive countries without an explicit clause approved at that level, except where criteria are set by the Security Council or the General Assembly. Competition narrowed to a region or a list of countries counts as limited international competition.

Export licences and dual use

The Solicitation policy requires the documents to state whether import or export licences are needed, including any restrictions in the country of origin, the dual-use nature of the goods and end-user conditions. For telecoms, measurement or encryption equipment made in Europe, this point often drives lead times more than origin does.

When building an offer, Sobetracom checks from Belgium the Data Sheet, the origin declared by each manufacturer and the applicable export regime. The origin clause varies between solicitations: the tender documents are what count, and any doubt should be raised as a written clarification request before the deadline.

Frequently asked questions

Does UNDP require goods made in a member country or in the European Union?
No. Under the ITB template, origin is open unless specific countries are listed in the solicitation's Data Sheet.
Can a Belgian company supply equipment made in Asia under a UNDP contract?
Yes, provided the Data Sheet does not exclude that country and neither the manufacturer nor the bidder is on a UN sanctions list or a World Bank debarment list.
Why do some UNDP solicitations still restrict origin?
Because the agreement with the project's donor may require it. The POPP then requires prior approval from the Chief Procurement Officer, and the restriction must appear in the documents.

Sources

  1. PNUD, POPP, modèle Invitation to Bid (ITB), Section 2 (October 2026)
  2. PNUD, POPP, Procurement Methods, version 19.0 (October 2026)
  3. PNUD, POPP, Procurement Overview and Principles, version 1.0 (October 2026)
  4. PNUD, POPP, Solicitation, version 9.0 (October 2026)
  5. PNUD, Qualifications and Eligibility (October 2026)

This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.

A project in Africa? Let's talk.

Tell us what you need and where it goes. We come back to you with first leads.