Donor · UNDP
UNDP: securities, advances and supplier payment
UNDP pays after delivery and rarely before. For an equipment supplier this is the first cash-flow fact: manufacturing and freight have to be financed, then the invoice has to be received and accepted. Bank guarantees, for their part, depend mainly on contract value.
The rules come from the POPP Solicitation policy, the invitation to bid (ITB) template and the general terms and conditions UNDP attaches to all its contracts for goods. They are set out below in the order a bidder meets them.
Updated on 21 October 2026
A bid security stated as a lump sum
A bid security is not automatic. The Solicitation policy generally advises one for contracts above USD 300 000 and puts the amount at 0.5% to 2% of the expected value. It must be stated as a rounded lump sum so as not to reveal the buyer's budget.
The ITB template sets out how it works: valid for at least 30 days beyond bid validity, original sent by courier, released to unsuccessful bidders no later than 30 days after bid validity expires. It may be forfeited if the bidder withdraws, rejects the correction of an arithmetical error, fails to sign the contract within 15 days or does not provide the performance security.
Performance security
Above USD 500 000 a performance security is mandatory; below that, the office may ask for one depending on risk. The recommended amount is at least 10% of the contract. It may take the form of a bank guarantee, an irrevocable letter of credit or retention money held until final acceptance.
It often covers the warranty period, installation and commissioning as well. It is returned within 30 days of contract completion. The issuing bank must be certified as a commercial bank by its country's central bank, and the wording follows UNDP's template, which cannot be changed without its legal office's approval.
Advances: capped and guaranteed
UNDP prefers not to pay advances and says so at solicitation stage. Where one is accepted, it may not exceed 20% of the offer price or USD 30 000, whichever is lower. The general terms add that, from that level, the advance is only paid against a bank guarantee or certified cheque for its full amount.
For equipment built to order, this cap weighs on the financing plan: on a large contract the advance stays small compared with the value of the goods.
Payment within 30 days of acceptance
Payment follows delivery and acceptance of the original invoice. The general terms set the period at 30 days from that acceptance, while UNDP's FAQ speaks of net 30 days from invoice or delivery, whichever is later. UNDP does not issue letters of credit to its suppliers.
The Schedule of Requirements may tie each payment to a milestone: pre-shipment inspection, inspection on arrival, installation, testing, training, then written acceptance. Proof of delivery includes at least the invoice, a certificate of conformity and the shipping documents. UNDP may withhold payment for non-compliant goods and set off any amount the supplier owes it.
Liquidated damages
Where timing is critical, the General Considerations of Contracting policy generally sets liquidated damages at 1% of the contract per week of delay, and at 10% termination becomes an option. The ITB template applies the same 10% cap.
Sobetracom builds these parameters into the price from the first manufacturer enquiries: cost of guarantees, payment period and acceptance schedule. Amounts and payment milestones vary with the Data Sheet, which is the document to take to the bank before submitting.
Frequently asked questions
- Does UNDP pay a deposit on order?
- Rarely. Where it agrees, the advance is capped at 20% of the offer price or USD 30 000, whichever is lower, and requires a bank guarantee from that level.
- How quickly does UNDP pay?
- The general terms provide for payment within 30 days of invoice acceptance, after compliant delivery.
- Is a performance security always required?
- It is mandatory above USD 500 000 and optional below, depending on the office's risk assessment. The recommended amount is at least 10% of the contract.
Sources
- PNUD, POPP, Solicitation, version 9.0 (October 2026)
- PNUD, POPP, Solicitation, version 9.0, et General Terms and Conditions for Contracts (Goods and/or Services) (October 2026)
- PNUD, POPP, modèle Invitation to Bid (ITB) (October 2026)
- PNUD, Frequently asked questions (procurement) (October 2026)
- PNUD, POPP, General Considerations of Contracting, version 8.0 (October 2026)
This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.