World Bank: putting together a compliant bid for goods

In an international tender financed by the World Bank, the Borrower does not draft its bidding document from scratch. Paragraph 5.24 of the Procurement Regulations requires it to use the Bank's Standard Procurement Documents, published at www.worldbank.org/procurement. For goods this is usually the Request for Bids Goods, in its edition revised in March 2025.

That shared framework helps suppliers, since forms and the order of documents look much the same from one country to another. It is also unforgiving: a document in the wrong place can be enough to disqualify a bid. Here is the structure to know.

Updated on 21 October 2026

A bid in 2 envelopes

The standard document splits the bid into a Technical Part and a Financial Part, delivered in 2 separate sealed envelopes inside an outer envelope marked "Original Bid". The Technical Part is opened and evaluated first, the Financial Part afterwards.

The most common trap is simple: the Technical Part must not contain any information on price. A discount, a spare parts price list or a priced option placed in the wrong envelope puts the whole bid at risk of being declared non-responsive. Spare parts prices requested as part of conformity should therefore go exactly where the document says.

Inside the Technical Part

The Letter of Bid, Technical Part, on the Section IV form with the text unaltered. The Bid Security or Bid-Securing Declaration, as the Bid Data Sheet requires. Written authorisation of the signatory. Evidence of the bidder's eligibility and qualifications. Evidence that the goods are eligible and conform to the requirements.

For conformity, the document expects an item-by-item description of the essential technical and performance characteristics, supported by literature, drawings or data, plus a statement of any deviations from the Section VII specifications. Brand names quoted by the buyer are descriptive only, so an equivalent may be offered if equivalence is shown. Section IV also includes a Technical Bid Checklist, a functional guarantees form and a declaration on sexual exploitation, abuse and harassment (SEA/SH).

Manufacturer's Authorization and local representation

A distributor or sourcing office that does not make the goods must, where the Bid Data Sheet requires it, attach a Manufacturer's Authorization on the prescribed form. It is normally required for critical or technically complex items. The sheet may also require a foreign bidder to show that it will be represented in the country by an agent able to handle maintenance, repairs and spare parts stocks.

Both documents depend on third parties, so start early. Getting a European manufacturer to sign an authorisation naming the right project and buyer often takes longer than writing the rest of the bid.

The Financial Part and pricing

It holds the Letter of Bid, Financial Part, and the Price Schedules. Goods manufactured abroad and to be imported are priced CIP at the named place of destination in the buyer's country, plus inland transport, insurance and local services to the project site. Trade terms follow the Incoterms edition stated in the Bid Data Sheet. Prices may be expressed in any currency, with no more than 3 foreign currencies in addition to the local one where the supplier wants payment in several.

Since 1 March 2025, international procurement using a standard document has been evaluated with Rated Criteria alongside price. Their weight depends on risk and value: between 20% and 30% for a moderate-risk, low-value purchase, under paragraph 5.50.

After award

The successful bidder must provide a Beneficial Ownership Disclosure Form; the Bank's guide for suppliers gives 8 business days from the Letter of Acceptance. Sobetracom works with manufacturers on authorisations, data sheets and CIP quotations, and checks which documents go into which envelope. The Bid Data Sheet of each tender overrides this summary and should be read again before submission.

Frequently asked questions

Which language should a bid be written in for a World Bank project in French-speaking Africa?
Paragraph 5.14 lets the Borrower choose English, French or Spanish for international procurement. The Bid Data Sheet states which; if the documents are issued in 2 languages, the bid may be written in either.
Can a reseller bid without being the manufacturer?
Yes, but where the Bid Data Sheet requires it, the reseller must attach a Manufacturer's Authorization on the Section IV form for each item concerned.

Sources

  1. Banque mondiale, Standard Procurement Document, Request for Bids Goods (deux enveloppes), édition de mars 2025, ITB 11 (March 2025)
  2. Banque mondiale, Procurement Regulations for IPF Borrowers, 7e édition, paragraphes 5.14, 5.24 et 5.50 (September 2025)
  3. Banque mondiale, A Beginner's Guide for Suppliers, 5e édition, avril 2025 (April 2025)

This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.