The financial terms of an AFD-financed contract are set by the project owner, but the February 2024 Guidelines frame the main points and AFD's February 2017 standard document for goods provides a complete model. Project owners often adopt it as it stands, so most of it can be anticipated.

One starting point matters: AFD is not the contractual payer. The Guidelines state that a supplier has no direct claim against AFD on the funds and bears alone the consequences of non-payment by the project owner.

Updated on 20 October 2026

Bid security or bid-securing declaration

Article 3.2.8 recommends a bid security for works, equipment and goods contracts. The project owner may replace it with a bid-securing declaration: a bidder who withdraws its bid, refuses to sign or fails to provide the performance security becomes ineligible for that owner's contracts for a period set in the dossier.

Where a security is required, the standard document accepts a bank demand guarantee, an irrevocable documentary credit or a banker's or certified cheque. An issuer based outside the buyer's country must have a correspondent there, and the security remains valid for 28 days beyond bid validity. The amount is stated in the bid data sheet.

Advance payment and performance security

Under article 3.3.1, any advance payment requires a bank demand guarantee for the same amount; the project owner may waive this only for an advance below EUR 10 000 and only if the dossier says so. A performance security and retention money are recommended for goods, and the project owner must be able to assign them to AFD on request.

In the standard document, the performance security is provided within 28 days of notification, usually for 10% of the contract price. It is released no later than 28 days after the supplier's obligations are completed, warranty included, so it runs throughout the equipment's warranty period.

A model schedule: 10, 80, 10

For goods supplied from abroad, the special conditions of the standard document propose a staged schedule. An advance of 10% is paid within 30 days of signature, against a bank guarantee for the same amount. On shipment, 80% of the price of the goods shipped is paid by confirmed irrevocable letter of credit, against the shipping documents. The remaining 10% is paid within 30 days of receipt, on the acceptance certificate.

The same model provides for liquidated damages, typically 0.5% per week, capped at a percentage of the price not exceeding 10%. These figures are indicative: only the special conditions of the published contract are binding.

CIP to destination, prices and taxes

Article 4.8 of the Guidelines requires Incoterms to be used and, preferably, prices quoted CIP to the place of destination: the supplier pays freight and insurance, but risk passes to the buyer once the goods are handed to the first carrier. The 2017 standard document still refers to Incoterms 2010, so the edition cited in the published dossier needs checking.

Bids are evaluated excluding the taxes and duties of the project owner's country, and the dossier must say for each whether it is exempt or paid by one of the parties. Price adjustment is not required under article 3.3.2 for delivery within 12 months, but is mandatory beyond 12 months.

Securing the financing of a delivery

Sobetracom supplied electrical and gas analysis and measurement equipment for a project supported by AFD in the DR Congo, without any contract with AFD itself. In deliveries of this kind, the task is to align bank guarantees, the letter of credit and the manufacturers' terms. The contract's tax arrangements and clearance at destination are checked with the project owner and the licensed customs broker before shipment.

Frequently asked questions

Does AFD pay the supplier directly?
The contract binds the supplier to the project owner alone. The Guidelines state that the supplier has no direct claim against AFD on the funds and bears the consequences of any non-payment itself.
Is an advance payment always secured?
Yes, by a bank demand guarantee for the same amount, except for an advance below EUR 10 000 where the dossier provides for that waiver.
Which Incoterm should be expected in an AFD-financed goods tender?
Preferably CIP to the place of destination, under article 4.8 of the Guidelines. The published dossier states the Incoterm and its edition.

Sources

  1. AFD, Directives pour la passation des marchés financés par l'AFD dans les États étrangers (AFD-R0097), février 2024, article 3.2.8 (February 2024)
  2. AFD, Documents d'appel d'offres, Marchés de fournitures, février 2017, IS 19 et 42, CCAG 18 et CCAP (February 2017)

This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.

A project in Africa? Let's talk.

Tell us what you need and where it goes. We come back to you with first leads.