GIZ: advance payment guarantee, payment terms and Incoterms
The financial terms of a GIZ purchase sit on 2 levels. The General Purchase Conditions, July 2023 version, set the framework: fixed prices, payment against documents, penalties and German law. Each contract's special conditions then set the advance, the guarantee required, the Incoterm and the place of delivery.
File 10059815, published in October 2026 for transformers delivered to Ukraine, shows a case that is very good for the supplier's cash flow but demanding about the quality of the bank.
Updated on 21 October 2026
A 100% advance against a bank guarantee
In this file GIZ pays an advance of 100% of the contract value against an advance payment guarantee that follows the attached template and is issued in writing on the bank's letterhead. Only first-class banks rated at least BBB- (Baa3) by an independent agency are accepted. A foreign bank without a rating can use an indirect guarantee from a German bank that meets those criteria.
The timetable is tight: GIZ may withdraw from the contract if the guarantee does not reach it within 10 days of award, by fax, as an original or by SWIFT message, or if the original does not arrive within 5 days of the fax. The only guarantee template among the tender documents is the advance payment guarantee; no bid security is provided for.
Payment against documents: invoice and shipping evidence
The General Purchase Conditions set fixed prices covering packing, delivery documents, transport, assembly and installation. The price is payable on the contractual date once GIZ has an itemised commercial invoice, the delivery documents and evidence of shipment. Depending on the Incoterm, that evidence may be a receipt from GIZ's forwarder, an ocean or FIATA bill of lading, or an air or road waybill.
GIZ's supplier page adds the formalities: an advance payment invoice labelled as such, a final invoice once delivery is confirmed, and foreign currency costs converted at the European Commission's InforEuro rate. The Ukrainian file asks for invoices in XRechnung format, compliant with EN 16931-1, or as PDF.
Penalties, retention and governing law
For late delivery, GIZ may charge a penalty of 0.2% of the agreed price per calendar day, capped at 5%. It may also retain 15% of the invoice amount until the end of the statutory warranty period if insolvency or liquidation proceedings are opened against the supplier.
The contract is governed by German law, excluding the UN Convention of 11 April 1980 on the International Sale of Goods, and the courts of Bonn and Frankfurt am Main have sole jurisdiction. A Belgian or French supplier should factor that into its risk assessment.
Incoterms and place of delivery
The general conditions refer to the Incoterms set in each contract. In file 10059815 the clause is DPU Ukraine (South-East), with delivery by 31.08.2027 at the latest and a factory quality inspection to be announced at least 2 weeks ahead. The supplier therefore carries transport to the destination and unloading.
A full advance does not remove the need to price the bank guarantee and the freight. Sobetracom helps manufacturers weigh those costs against the delivery schedule. Every contract sets its own terms, so the advance, the Incoterm and the deadlines should be checked in the special conditions published with the notice.
Frequently asked questions
- Does GIZ ask for a bid security?
- File 10059815 does not: the only template among its documents is the advance payment guarantee, which the successful bidder provides in order to receive the advance.
- Which bank can issue the advance payment guarantee?
- In this file, a first-class bank rated at least BBB- (Baa3). A foreign bank without a rating can have its guarantee backed by a German bank that meets those criteria.
- What penalty applies to late delivery?
- The July 2023 General Purchase Conditions provide for 0.2% of the agreed price per calendar day of delay, up to 5% of the price.
Sources
- GIZ, Besondere Vertragsbedingungen et liste des Vergabeunterlagen, dossier 10059815 (October 2026)
- GIZ, General Purchase Conditions, as at July 2023, sections 2.3, 3.1, 3.2 et 5.1 (July 2023)
- GIZ, Materials and equipment (suppliers), facturation et paiement (October 2026)
This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.