Donor · French Development Agency (AFD)
AFD: international or national tender, request for quotations or direct contracting
AFD does not itself run the procurement for the projects it finances abroad. Contracts are signed by the project owner, a ministry, state company or local authority, which organises competition under its own laws as supplemented by AFD's February 2024 Guidelines. AFD reviews and gives or withholds its no-objection, but is not a party to the contract.
This guide covers the procurement methods set out in the Guidelines, their thresholds, and how the choice of method is fixed early on in the procurement plan.
Updated on 20 October 2026
The project owner buys, AFD reviews
Under article 1.2.4, the project owner alone is responsible for the bidding documents, evaluation, award, contract and handling of complaints. AFD finances a beneficiary under a financing agreement, and the Guidelines state that no contractual link exists between AFD and anyone other than that beneficiary. A supplier's exchanges with AFD therefore create no commitment on AFD's part.
Everything starts with the procurement plan, which covers at least the next 18 months and receives AFD's no-objection. It shows the estimated value, procurement method and timetable of each contract. Splitting a purchase to slip under a threshold is expressly prohibited.
Goods and equipment: two very different thresholds
Article 2.1 requires international competitive bidding, unless AFD expressly agrees otherwise, above EUR 5 000 000 excluding taxes for works or equipment contracts, and above EUR 200 000 for goods and services contracts. It also requires it whatever the value where too few qualified firms exist in the country.
The gap between the two thresholds makes the classification of a contract decisive. A batch of standard items counts as goods and goes international from EUR 200 000; installed plant counts as equipment. The procurement plan and notice show which category applies. Below the threshold the project owner runs a national tender, which may not bar foreign companies.
Requests for quotations
For small standard contracts, article 2.3 allows a request for quotations below EUR 300 000 for works or equipment and below EUR 200 000 for goods and services, where local law permits. The project owner consults a shortlist of 3 to 6 firms whose qualifications, eligibility and absence of conflict of interest it has checked, and selects the lowest technically compliant quotation.
No advertisement is required, so a supplier is only consulted if the project owner or its technical assistance already knows it.
Direct contracting: the exception, with AFD's agreement
Article 2.4 allows direct contracting only with AFD's prior agreement and under cumulative conditions: the law permits it, the lack of competition is justified by extreme urgency or a sole provider, the awardee is qualified and the price is in line with the market. Below EUR 40 000 excluding tax, the urgency or sole-provider justification is not needed. Above it, the project owner sends a consultation letter setting out specifications and conditions, and such contracts can only be reviewed ex ante.
How bids are ranked
For goods and equipment, article 4.4 awards the contract to the substantially responsive bid evaluated as lowest, provided the bidder is qualified. A bid 20% or more below the project owner's estimate triggers a request for clarification and a price breakdown, with no automatic rejection. Financial negotiation is prohibited unless AFD expressly agrees.
Sobetracom, which supplied measurement equipment for a project supported by AFD in the DR Congo, without any contract with AFD itself, helps identify a contract's category and procedure before consulting manufacturers. Thresholds may be varied with AFD's agreement, so the project owner's notice is the reference.
Frequently asked questions
- From what value does an AFD-financed goods contract go to international tender?
- Above EUR 200 000 excluding taxes under the February 2024 Guidelines, unless AFD expressly agrees otherwise. For equipment and works the threshold is EUR 5 000 000.
- Can I contact AFD to be invited to bid?
- No. The project owner runs the procedure and chooses whom to consult; the Guidelines state that there is no contractual link between AFD and suppliers.
- Is a request for quotations advertised?
- No, it goes to a shortlist of 3 to 6 firms drawn up by the project owner.
Sources
- AFD, Directives pour la passation des marchés financés par l'AFD dans les États étrangers (AFD-R0097), février 2024, article 1.2.4 (February 2024)
This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.