AfDB: securities, advances and payment schedule in a goods contract

The financial terms of a goods contract financed by the African Development Bank come from 2 texts: the standard document for goods, revised in February 2018, which sets the mechanics of the securities, and the Operations Procurement Manual, revised in May 2026, which gives reference points for the payment schedule. The standard document leaves the terms of payment blank, for the Borrower to fill in through the Particular Conditions of Contract.

The Manual itself warns that the percentages it quotes are indicative and depend on the procedure and the risks. The figures below are for planning, not a substitute for reading the bidding document.

Updated on 21 October 2026

Bid security: form and duration

The Bid Data Sheet chooses between a bid security and a Bid-Securing Declaration, to be submitted in original. The security may be an unconditional guarantee from a bank or surety, an irrevocable letter of credit or a certified cheque, from a reputable source in an eligible country. The Manual is strict about form: a copy or fax leads to rejection of the bid.

The security must remain valid for 28 days beyond bid validity. If the buyer asks for validity to be extended, a bidder who agrees also extends its security to 28 days beyond the new date. Where an insurer or bonding company outside the buyer's country issues the security, it needs a correspondent financial institution there to make it enforceable.

Performance security: mandatory under OCBI

The Manual makes performance security mandatory for contracts let under Open Competitive Bidding International. It is an irrevocable and unconditional undertaking payable on first demand, typically for 5 to 10% of the contract value, and may be raised depending on risk.

The standard document sets the timing: the successful bidder furnishes it within 28 days of notification of award. Failing that, the award is annulled and the bid security forfeited. The model Particular Conditions provide for its discharge no later than 28 days after the supplier's obligations are completed.

The typical payment schedule for goods

For the supply of goods, the Manual describes a schedule in 3 stages. An advance of 10% of the price, normally paid within 30 days of signature, against a receipt and a bank guarantee for the same amount. Then 80% on shipment or delivery, against the documents specified in the contract. Finally the remaining 10%, normally within 30 days of the acceptance certificate. A portion may be retained to cover the warranty period.

For a supply, installation and commissioning contract, the Manual cites a typical advance of 10 to 15% and a final payment of 10% on final acceptance. The supplier should then plan for longer financing, since part of the price depends on commissioning on site.

CIP, letters of credit and payment risk

Imported goods are priced CIP at the place of destination, and import duties and taxes remain with the Borrower. The Manual also mentions letters of credit or escrow accounts among the measures that may be considered where late payment is a risk in a given country or with a given buyer. This is not a general rule, so the supplier should check the Particular Conditions to see whether a letter of credit is provided for.

Sobetracom helps suppliers build the cost of securities and pre-financing into their price and check the required forms with their bank. The signed Particular Conditions remain the only binding text.

Frequently asked questions

Is an emailed copy of the bid security enough?
No. The Manual provides for rejection where the security or declaration is a copy or fax rather than the original, unless the bidding document provides otherwise, for example for electronic submission.
What performance security amount should be planned for?
The Manual typically cites 5 to 10% of the contract value, which may be raised according to risk. The exact amount is in the Particular Conditions.
When is the advance paid?
The Manual's indicative schedule has a 10% advance normally paid within 30 days of signature, against a bank guarantee for the same amount.

Sources

  1. Banque africaine de développement, SBD Procurement of Goods, février 2018, ITB 19, ITB 38 et PC (February 2018)
  2. Banque africaine de développement, Operations Procurement Manual, partie A, volume 1, D1.2.25 à D1.2.28 (May 2026)

This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.

A project in Africa? Let's talk.

Tell us what you need and where it goes. We come back to you with first leads.