Donor · African Development Bank
AfDB: procurement methods for goods and which system applies
In a project financed by the African Development Bank, the contract is let by the Borrower, usually a ministry or an executing agency. The August 2015 Procurement Policy puts it plainly: the Borrower is responsible for the integrity of the process from planning through to contract management, and the Bank checks through reviews that the Financing Agreement is respected.
What sets the AfDB apart is the weight given to national systems. Since the 2015 reform the Bank has sought to rely on the Borrower's own procurement rules wherever they meet its principles. A single project can therefore mix lots procured under the national code with others under Bank rules.
Updated on 21 October 2026
3 families of methods
Paragraph 8.5 of the Policy distinguishes Open Competitive Bidding (OCB), Limited Competitive Bidding (LCB) and Direct Procurement (DP). OCB, with wide advertising and no restriction on eligible bidders, is the normal route for goods. LCB, which may take the form of priced quotations from a limited number of suppliers, is used for simple low-value goods or for specialised equipment where few suppliers can respond. Direct Procurement remains exceptional.
The Operations Procurement Manual, revised in May 2026, sets out the variants. Under Request for Quotations, the buyer asks foreign, national or local suppliers for written quotations. Under Shopping, it approaches at least 3 suppliers. Direct Procurement may be justified to standardise an equipment fleet, buy proprietary equipment available from a single source, extend an existing contract or respond to a natural disaster.
OCBI or national rules
The Manual states that Open Competitive Bidding International (OCBI) is used for relatively complex and large contracts. It also makes a point that often surprises suppliers: OCB is the preferred method but not the default one. The first methods to consider are those of the Borrower's procurement system, where the Bank has found it acceptable for the operations concerned.
For a European supplier the consequence is practical. A contract procured under the national code follows the country's advertising rules, deadlines and often its language. An OCBI contract follows the Bank's standard document, written in English or French, the 2 official languages the Policy provides for.
No country threshold table
Unlike some other donors, the AfDB does not publish a country-by-country threshold table in its Manual. The Manual states that there are no pre-set monetary thresholds by country or sector, and that the method is chosen on the basis of the market and context, then recorded in the Project Appraisal Report and the Procurement Plan.
A few figures do give bearings. The standard document for goods, revised in February 2018, says it is for contracts above UA 300,000 procured through international competitive bidding. And where the national system is used, goods contracts below UA 1,000,000 are open to firms from all countries, which lifts the member-country condition.
Reading the Procurement Plan
The project's Procurement Plan shows, lot by lot, the method, the applicable system and the type of Bank review. Sobetracom uses it to spot goods lots open to foreign firms and to line up manufacturer quotations and technical documentation in good time. The method actually chosen appears in the notice, and it is that method which sets the deadlines and the documents required.
Frequently asked questions
- Does the AfDB buy the equipment for its projects itself?
- No. The Borrower runs the procurement and signs the contracts. The Bank's purchases for its own operations go through a separate unit, Corporate Procurement.
- Is a contract procured under an African country's national code open to a Belgian company?
- The Manual says that under the Borrower's system, goods contracts below UA 1,000,000 are open to firms from all countries. The exact conditions are in the notice and bidding document.
- Is there a single threshold above which the AfDB requires international bidding?
- No. The Manual rules out pre-set thresholds by country or sector; the method is set project by project in the Procurement Plan.
Sources
- Banque africaine de développement, Procurement Policy for Bank Group Funded Operations, août 2015, paragraphes 1.5, 8.1 et 8.7 (August 2015)
- Banque africaine de développement, Operations Procurement Manual, partie A, volume 1, chapitre D2 (May 2026)
- Banque africaine de développement, SBD Procurement of Goods (février 2018) ; OPM partie A, volume 1, A2.1.7 (February 2018)
- Banque africaine de développement, Resources for businesses (October 2026)
This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.