Donor · UNICEF
UNICEF: procurement methods, long-term arrangements and published thresholds
UNICEF is not a donor financing a borrower that runs its own tenders: UNICEF itself conducts the procurement and signs the purchase order. It does so for its own programmes and, through its procurement services, for governments, NGOs, other UN agencies, international financial institutions, foundations and universities. Either way, the supplier's only counterparty is UNICEF.
The internal thresholds that decide which method is used are not set out on the Supply Division's public pages. What is published is the standard solicitation documents, the evaluation rules and the form of long-term arrangements, and this guide is based on those texts.
Updated on 21 October 2026
Invitation to bid: price and lead time
The invitation to bid template for goods describes a two-stage evaluation. UNICEF first checks compliance with the mandatory requirements, and a bid that misses one is rejected outright. It then judges whether the products are commercially and technically acceptable and of the required quality, comparing prices on the Incoterm set in the documents.
The award criterion is distinctive: UNICEF selects the bid offering the combination of the lowest acceptable prices and the shortest lead time. Lead time is therefore no formality, and it is measured again during performance against what the supplier promised.
Request for proposal: technical without price
For more complex goods, the request for proposal template separates the technical proposal, which must contain no price information, from the price proposal. UNICEF states that it welcomes innovative solutions. The template's award criterion is still the combination of lowest acceptable prices and shortest lead time, after the mandatory checks, unless the documents add their own criteria.
In both cases a new supplier should know that UNICEF may first award only a limited quantity until satisfactory performance is established. UNICEF may also split an item between several suppliers, and it notifies only the successful bidders.
Long-term arrangements
For repeat purchases, UNICEF concludes Long Term Arrangements. The template for goods is clear about what it commits: the supplier sells whatever quantities UNICEF orders, if any. There is no minimum quantity and no exclusivity, and prices stay fixed for the whole term, as the most favourable offered to any customer.
Each purchase order under the arrangement must be countersigned within 5 working days. UNICEF may renew the arrangement by giving notice at least 30 days before it ends, and may share it with other UN organisations. For a manufacturer, everything is decided at the tender that fixes the price for several years of uncertain orders.
Shortlisting and published awards
Not every procedure is open. According to the e-submission instructions, for some purchases UNICEF runs a qualification-based shortlisting before launching the tender; only shortlisted firms receive the invitation, which appears under ‘my tenders’ on UNGM.
Downstream, the Supply Division publishes its awards: since 1 May 2019, every contract of US$500,000 or more, and long-term arrangements with estimated spend at that level. The lists show who supplies what, and on what scale.
Working from Belgium, Sobetracom reads each tender to identify the method, the evaluation Incoterm and the weight given to lead time, then consults manufacturers. Templates and practice change, so the tender documents remain the reference.
Frequently asked questions
- Does UNICEF buy on behalf of governments?
- Yes, through its procurement services, open to governments, NGOs and other partners. The supplier is still contracted by UNICEF, which delivers CIP to the port of entry through its freight forwarders.
- Does a long-term arrangement guarantee orders?
- No. The UNICEF template sets no minimum quantity and the arrangement is non-exclusive.
- Does lead time count in the award?
- Yes. UNICEF templates award to the combination of lowest acceptable prices and shortest lead time.
Sources
- UNICEF Supply Division, Invitation to Bid (ITB) for goods, Part III (October 2026)
- UNICEF Supply Division, Request for Proposal (RFP) for goods, document type (October 2026)
- UNICEF Supply Division, Long-term arrangement (LTA) for goods, contractual provisions (October 2026)
- UNICEF Supply Division, Bidders' instructions on UNICEF e-submission system (October 2026)
- UNICEF Supply Division, Getting started (procurement services) (October 2026)
- UNICEF Supply Division, Contract awards (October 2026)
This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.