Donor · UNOPS
UNOPS: solicitation methods and thresholds for goods
UNOPS is not a donor in the sense of a development bank. It is a United Nations entity that buys goods, services and works itself on behalf of its partners. According to its Supplier Resource Centre, it procures over $1 billion a year from a base of more than 6,000 suppliers in over 170 countries. A supplier therefore contracts with UNOPS, not with the ministry or donor funding the project.
The rules sit in the Procurement Manual, Revision 7, supplemented by authoritative revisions. For an equipment supplier the one that matters most is Revision 2024/07 of 20 September 2024, which raised the thresholds. This guide covers those thresholds, the types of competition and the cases in which UNOPS may deal with a single supplier.
Updated on 21 October 2026
Informal and formal methods
Section 6.3 of the Manual sets out 4 methods. Shopping and the request for quotation (RFQ) are informal; the invitation to bid (ITB) and the request for proposal (RFP) are formal. The choice depends on value, complexity, market conditions and the partner's requirements, and the Manual forbids splitting a requirement into several shopping or RFQ exercises to avoid a formal method.
Since Revision 2024/07, shopping covers purchases below US$ 10,000, the RFQ runs from US$ 10,000 to under US$ 250,000, and an ITB or RFP is required from US$ 250,000. Before the revision the steps were US$ 5,000 and US$ 50,000, and the table in the 2021 PDF still shows them alongside a note on the amendment. An RFP may still be used below US$ 250,000 where it suits the requirement.
ITB or RFP: two ways of evaluating
In an ITB the technical and financial parts form a single document. Each requirement is assessed on a pass/fail basis and the award goes to the lowest-priced substantially compliant bid, delivery terms included. It is the natural route for equipment described by a complete specification, such as a generator set or a batch of tools.
In an RFP the supplier submits technical and financial proposals in separate envelopes. The technical proposal must first reach a minimum score, normally 60% or 70% of the points, before the financial proposal is opened. The technical/financial weighting is stated in the documents: 80%-20%, 70%-30%, 60%-40% or 50%-50%, with price weighing more heavily the simpler the requirement.
Open, limited or direct competition
Section 6.2 makes open competition, international or national/regional, the default: the notice is public and any eligible supplier may respond. A national tender may be justified where buying locally lowers the total cost, but the Manual states that a well-qualified international supplier expressing interest is not automatically excluded and competes on the same terms.
Limited competition, restricted to a short list drawn from an expression of interest, a pre-qualification or market research, needs prior written approval from the procurement authority, and UNOPS must aim for at least 3 offers. For a manufacturer, answering expressions of interest and pre-qualifications is how to get onto those lists, which a public notice never reveals.
When UNOPS deals with one supplier
Section 6.8.1 lists the exceptions to formal methods allowed under Financial Rule 118.05. They include the absence of a competitive market (a monopoly, prices fixed by law, a proprietary product), standardisation after a recent purchase where compatibility with existing equipment requires it, cooperation with another United Nations organisation, such as an order placed against another agency's long-term agreement, and genuine exigency. A brand alone does not justify an exception where several sources exist.
Even under direct contracting, section 6.6.6 requires UNOPS to define the requirement, request an offer against its General Conditions of Contract and check that the price is reasonable.
Minimum bidding periods
Table 4 of the Manual sets minimum bidding periods in calendar days: 5 for an RFQ, 15 for an ITB for goods and 21 for an RFP. The procurement authority may shorten them for good reason, and they do not apply to direct contracting or emergency procedures. A 5-day RFQ leaves little time to obtain a manufacturer's quote, so monitoring has to be daily.
Working from Belgium, Sobetracom identifies the method, deadline and evaluation approach in each notice, then consults manufacturers against the specification. The thresholds changed in 2024 and may change again: only the documents of each tender set the applicable rules.
Frequently asked questions
- From what value does UNOPS issue an ITB or RFP for equipment?
- Since Revision 2024/07 of 20 September 2024, from US$ 250,000. Below that an RFQ is enough, and under US$ 10,000 simple shopping.
- Who does the supplier sign with when UNOPS buys for a ministry?
- With UNOPS. It buys on behalf of its partners and applies its own Manual, solicitation templates and General Conditions of Contract.
- Can a European company bid in a UNOPS national tender?
- Yes. Under section 6.2, a qualified international supplier that expresses interest in a national or regional tender is not automatically excluded.
Sources
- UNOPS, Authoritative Revision Ref. 2024/07 to the Procurement Manual Rev. 7 (October 2026)
- UNOPS, Procurement Manual, Revision 7, section 6.3 (October 2026)
- UNOPS, Supplier Resource Centre (October 2026)
This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.