Before reading any threshold, it helps to know who is actually running the tender. In EU external action the buyer is not always the Commission: depending on the management mode set in the financing decision, it may be the Commission itself, an authority in the partner country, or another organisation applying its own rules.

This guide summarises, from PRAG 2025, the procedures and thresholds that apply to supply contracts, and the cases in which the buyer may negotiate directly with a supplier.

Updated on 20 October 2026

Identifying the contracting authority

Section 2.2 of the PRAG sets out the management modes. Under direct management, the Commission, at headquarters or in an EU Delegation, acts on behalf of the partner country: it publishes, evaluates, handles complaints and signs. Under indirect management with the partner country, the contract is concluded by the body designated in the financing agreement, often a ministry or public agency; with ex ante controls, the Commission first approves the tender dossier, then the evaluation results, and endorses the contract.

The last case is indirect management entrusted to an international organisation or a Member State cooperation agency. That entity's own rules then apply, following a positive pillar assessment, instead of the PRAG. An "EU-funded" contract may therefore follow the procedures of a UN agency or a national agency, and the notice will say so.

The supply thresholds

For supply contracts, sections 2.6.1 and 4.2 set the following scale. From EUR 300 000, an international open tender is mandatory. Above EUR 100 000 and below EUR 300 000, a local open procedure may be used. Below EUR 100 000, the simplified procedure applies. Up to EUR 20 000 the buyer may award on a single tender, and up to EUR 2 500 it may simply pay against an invoice. By comparison, international tendering for works only starts at EUR 5 000 000.

Thresholds are calculated on the maximum budget for the contract, co-financing included. Splitting a purchase to stay under a threshold is prohibited, and where there is doubt the guide recommends using the procedure for the higher threshold.

Local open and simplified procedures

In a local open procedure, the notice appears in the partner country's official journal or equivalent local media, with at least 30 days before the deadline. The PRAG is clear on a point that matters to European suppliers: the buyer may not require registration in the partner country or past contracts won there. Up to EUR 150 000 it may waive the performance guarantee.

Under the simplified procedure no notice is published: the buyer invites at least 3 companies it has selected and justified. In practice a supplier needs to be known to buyers before the tender, because there is nothing to find online.

Negotiated procedure and award criterion

The negotiated procedure remains the exception. Section 4.2.6.1 allows it in particular where no suitable tender was received, where only one operator can deliver for technical reasons or because of exclusive rights, in cases of extreme urgency caused by unforeseeable events, or for additional deliveries where a change of supplier would cause technical incompatibility.

Otherwise, the contract goes to the cheapest technically compliant tender. Price is the only criterion for supplies without ancillary services, although life-cycle costs may be included where the specifications provide for it. Under the 2021-2027 framework there is no preference for firms from ACP States, unlike earlier EDF programmes, for which the PRAG keeps a 15% price preference.

Read the notice before pricing

Working from Belgium, Sobetracom starts by identifying the management mode, procedure and funding source in the notice, then consults manufacturers against the specifications. The thresholds and negotiation cases described here come from the PRAG, which is not legally binding: each procedure's contract notice remains the reference.

Frequently asked questions

From what value is an EU-funded supply contract advertised internationally?
Under PRAG 2025, from EUR 300 000, through an international open tender published in the Official Journal of the EU and on the Funding & Tenders Portal.
Does an EU Delegation buy the equipment itself?
Under direct management, yes: the Commission is the contracting authority. Under indirect management, the partner-country body named in the financing agreement buys, under Commission oversight.
Can a European company bid in a local open procedure?
Yes. The PRAG prohibits any condition restricting participation by eligible firms, such as a requirement to be registered in the partner country.

Sources

  1. Commission européenne, DG INTPA, PRAG 2025, section 2.2 (October 2026)