GIZ: procurement procedures, thresholds and country offices

In a GIZ project the buyer is usually GIZ itself. Germany's federal enterprise is not a bank lending to a government that then runs the tenders: it orders the equipment for its projects directly, from its head office or its country offices, and hands it over to partners afterwards. According to its report on 2024, it ordered 235 million euros' worth of materials and equipment that year.

The procedure turns on the contract value relative to the EU thresholds and on where the contract is placed, at head office in Germany or in the partner country.

Updated on 21 October 2026

Above the thresholds: the VgV

GIZ's report explains that it is a contracting authority within the meaning of Section 99 (2) of the German Act against Restraints of Competition (GWB). For contracts above the EU thresholds it is directly bound by procurement law, and the Procurement Regulation (VgV) governs supplies and services. In 2024 the threshold for supplies and services was 221,000 euros.

For contracts launched from 1 January 2026, the threshold for contracting authorities other than federal government bodies is 216,000 euros excluding VAT, according to the law firm CMS. In an open procedure, Section 15 of the VgV sets a time limit for receipt of bids of at least 35 days, which can be cut by 5 days where electronic bids are accepted and can fall to 15 days only in a justified emergency.

Below the thresholds: the UVgO

Below the thresholds, procurement law takes the form of administrative rules that do not bind GIZ directly. Its General Agreement with the federal government nevertheless requires it to apply them, and for supplies that means the Sub-threshold Procurement Regulation (UVgO). Section 8 of that text provides for public tendering, restricted tendering with or without a prior competition, and negotiated award with or without a prior competition.

The buyer may choose freely between public tendering and restricted tendering preceded by a competition; the other forms are allowed only in the cases listed. On GIZ's tender platform, each notice states whether it falls under the VgV or the UVgO.

Head office or country office: who awards

The 2024 report sets out a division of labour. Head office awards contracts relevant to the EU single market and approves local purchases above set value limits: 50,000 euros for materials and equipment and 100,000 euros for services and construction. Country offices award contracts to firms in the partner country or region.

In 2024, 20% of procurement was carried out at decentralised level, in almost 120 partner countries. For equipment, head office ordered 173 million euros' worth and country offices 62 million. A European manufacturer will therefore mostly deal with head office procedures advertised in Germany.

Financing agreements: a separate channel

Part of the money does not flow through GIZ tenders at all. In 2024 it concluded 840 million euros of financing agreements with partner implementing agencies and non-profit organisations. The recipients then implement the funded measures themselves, applying the German general conditions known as ANBest-P.

In that case the tender is issued by the recipient, not by GIZ. Sobetracom helps buyers and suppliers establish who is actually running the procurement before a bid is prepared. Thresholds and procedures change, and each contract's notice and documents remain the reference.

Frequently asked questions

Does GIZ run its own tenders or does the partner country?
For project equipment, GIZ orders directly, from head office or its country offices. Where it signs a financing agreement, however, the recipient implements the measures and carries out its own purchasing.
What is the minimum time limit for a GIZ open tender above the thresholds?
Section 15 of the VgV sets at least 35 days from the day after the notice is sent, reducible by 5 days if electronic bids are accepted, with a floor of 15 days in a justified emergency.
From what value must a country office have an equipment purchase approved?
According to GIZ's 2024 report, local purchases of materials and equipment above 50,000 euros require head office approval.

Sources

  1. GIZ, Procurement and financing by GIZ 2024, section 3.2 (Legal framework) (December 2025)
  2. CMS Hasche Sigle, « Neue EU-Schwellenwerte und nationale Anpassungen ab dem 1. Januar 2026 » (January 2026)
  3. Vergabeverordnung (VgV), § 15 (October 2026)
  4. Unterschwellenvergabeordnung (UVgO), § 8, publiée par le ministère fédéral de l'Économie (February 2017)

This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.