Import guide · DR Congo
Getting equipment into DR Congo: Matadi, transit ports and corridors
DR Congo is vast but has only a narrow Atlantic coastline, 22 miles long according to The Maritime Executive. The choice of route therefore depends less on the distance from Europe than on the final destination. Kinshasa and the west are served through the Congo River estuary, whereas Katanga, the Kivus or Ituri are often easier to reach through neighbouring countries' ports.
For a project, the route determines lead times, the number of transhipments, transit paperwork and a large share of the landed cost. This guide sets out the options as described by OGEFREM and the trade press as of February 2026.
Updated on 20 October 2026
Matadi and Boma: the western gateway
Matadi, on the left bank of the Congo River, remains the country's main seaport, with Boma further downstream. OGEFREM publishes the schedules of vessels calling there. However, the port lacks the draught for large vessels, and in February 2026 Ecofin reported a memorandum of understanding with AD Ports to develop a multi-purpose terminal.
On formalities, the DGDA reports that average clearance time at Matadi fell from 10 to 3 days in January 2018, and to 1 day at the MGT terminal. Those figures assume a complete file; they exclude onward transport to Kinshasa and port congestion.
Transit ports for the east and south
Without a suitable seaport of its own for every region, part of the DRC's foreign trade moves through neighbouring ports: Dar es Salaam and Mombasa on the Indian Ocean, and Lobito, Luanda and Pointe-Noire on the Atlantic. For deliveries to Lubumbashi, Goma or Bukavu, these routes avoid crossing the country from the west.
Each transit adds its own formalities in the country crossed, a road or rail leg to the border and a destination attestation (AD) that takes over from the FERI. OGEFREM is also building dry ports at Kasumbalesa in Haut-Katanga and Kalamba-Mbuji in Kasaï Central to handle these overland flows.
Banana: a deep-water port under construction
Banana port, at the mouth of the river, is meant to remove the draught constraint. DP World has appointed Mota-Engil for the first phase: a 600 m quay with 18 m of depth, designed for 450,000 TEU a year and 30 hectares of storage, according to The Maritime Executive in March 2025. Until it is operating it cannot be part of a logistics plan, but it is worth watching for multi-year projects.
Air freight and preparing the consignment
For urgent, low-volume or fragile equipment, air freight remains the answer, and OGEFREM lists flights serving Kinshasa, Lubumbashi and Goma. Switching transport mode along the way requires the importer's agreement and may mean amending the DIB.
In every case, the final invoice must separate the main carriage from road transport outside and inside the DRC, and cargo insurance must be paid to a company based in the DRC. From Belgium, Sobetracom compares routes and forwarders' quotes and organises container stuffing and sealing, and our relays in DR Congo follow the goods to the delivery site. Transit conditions change with neighbouring countries, so the chosen route should be confirmed with the forwarder and the buyer's licensed broker before booking.
Frequently asked questions
- For delivery to Lubumbashi, is Matadi or a neighbouring port the better option?
- Haut-Katanga is often served through neighbouring countries' ports, and OGEFREM is building a dry port at Kasumbalesa. Going through Matadi means crossing much of the country. The choice is made case by case, comparing lead times, transhipments and transit costs.
- Can Banana port be used yet?
- It was still under construction as of February 2026, according to Ecofin. It should not be included in a transport plan until commercial operations are confirmed.
- Does OGEFREM publish reference freight rates?
- Yes. It publishes reference freight prices, updated monthly for all routes. They are a benchmark for assessing a transport offer, not a substitute for a quotation.
Sources
- Agence Ecofin, « DR Congo, AD Ports sign MoU for multi-purpose terminal at Matadi » (February 2026)
- The Maritime Executive, « DRC's Banana Port achieves construction milestone » (March 2025)
- OGEFREM, page Services (October 2026)
- Agence congolaise de presse (ACP), « Fickin : l'Ogefrem invite les opérateurs économiques à souscrire à la FERI, FERE et AD » (August 2025)
- Bureau Veritas, fiche « Pre-export verification of imports for the Democratic Republic of Congo », Rev. 26 (June 2024)
- DGDA, page SYDONIA (October 2026)
This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.