Overhead cranes for workshops and power plants in Africa: getting the specification right

An overhead crane is not bought like a machine standing on the floor. It becomes part of the building: its girder runs on a runway, its loads go down into the columns, and its service life depends on how it will really be used. A thin specification produces either an oversized crane or a hoist that wears out within a few years.

For a fabrication shop, a warehouse or a power plant under rehabilitation, this page covers the data to collect, the standards to require and the delivery constraints specific to cranes.

Updated on 20 October 2026

Core data for the specification

A handful of values describe the crane: safe working load, span between rail centres, height of lift under the hook, speeds (hoist, cross travel, long travel) and configuration, single or double girder, top-running or underhung. Add the building dimensions: rail level, clear height under the roof structure and hook approaches at each end.

Duty class matters as much as capacity. ISO 4301-1:2016 classifies cranes and their mechanisms by the total number of working cycles over the design life, the load spectrum factor (how often each load level is handled) and average displacements. Describing actual use honestly, occasional lifts in a turbine hall or continuous handling in a shop, lets the manufacturer size the hoist, brakes and wheels correctly.

Standards to cite

In Europe, the product standard is EN 15011:2020, covering bridge and gantry cranes on rails as well as stationary gantries. It excludes the lifting of persons and refers light crane systems, such as wall-mounted and workshop jib cranes, to EN 16851. Structural design relies on EN 13001-1:2015, which deals with tilting, strength and fatigue limits, buckling, and temperature and deformation limits.

The hoist falls under EN 14492-2:2019, which covers powered rope, chain and belt hoists with or without trolleys. Requiring conformity with these standards, plus a declaration of conformity under the Machinery Directive, gives a sound basis for comparing European and non-European suppliers.

Building, power and site conditions

The runway is often the weak point on rehabilitation projects: worn rails, unchecked runway beams, unknown alignment. A building survey and a calculation of the supports, by a local engineer or the manufacturer, avoid delivering a new crane onto a structure that cannot carry it.

For power, choose between a festoon system and a conductor rail, and protect the drives if the supply is unstable. In a hot, dusty hall, ask for motors and panels with a suitable degree of protection, and for a radio remote control operating on a frequency authorised in the country of installation.

Delivering and erecting long girders

Main girders are the most awkward packages. According to Hapag-Lloyd's specifications, a 40' High Cube flat rack offers 11,652 mm between corner posts and 2,224 mm of width; heavy loads must rest on the main girder of the flat rack, and the allowable payload depends on the resting length. A longer span means either a bolted sectional girder or break bulk shipment.

Erection requires a mobile crane, a qualified crew and a load test at commissioning, with a signed report. Include in the offer erection supervision by the manufacturer, training for crane operators and the site technician, and a set of wear parts: brake linings, rope or chain, contactors and limit switches.

How Sobetracom works on cranes

In Nigeria, Sobetracom supported a private company in buying overhead cranes, alongside a press brake of up to 10 m and laser cutting equipment for the same group of workshops. We turn the site's needs into a specification, consult several manufacturers, compare offers on duty class, standards applied and erection, then coordinate inspection and freight. Import formalities should be checked for each shipment with the client's licensed customs broker.

Frequently asked questions

Single girder or double girder?
It depends on capacity, span and available headroom. A double girder gives more height under the hook and suits long spans; a single girder is lighter on the building. The manufacturer decides from the hall dimensions.
Will a crane girder fit on a flat rack?
Up to 11,652 mm between corner posts on a 40' High Cube flat rack, according to Hapag-Lloyd. Beyond that, a sectional girder or break bulk shipment is needed.
Why state actual use rather than just capacity?
Because ISO 4301-1:2016 sizes mechanisms by number of cycles and load spectrum. A crane in continuous production is not designed like a maintenance crane.

Sources

  1. Genorma, fiche EN 15011:2020 (October 2026)
  2. Genorma, fiche ISO 4301-1:2016 (October 2026)
  3. Genorma, fiche EN 13001-1:2015 (October 2026)
  4. Genorma, fiche EN 14492-2:2019 (October 2026)
  5. Hapag-Lloyd, Container Specification (October 2026)
  6. Sobetracom, références clients (September 2026)

This page summarises public sources as of the date shown. It does not replace the official text: check it before committing to a purchase, a bid or a shipment.